The ground under it was tendered in 2012. Both ends of that are public; nobody puts them together.
The land under Waterwoods
HDB put this parcel out to tender and names Waterwoods as what was built on it. Everything below is from that tender: the dates, the winning price, and the 7 bids that came in.
- Tender launched15 Oct 2012
- Tender closed6 Dec 20127 bids received
- Awarded10 Dec 2012Sing Holdings Limited
- Winning tenderS$162,100,000S$3,777 per sq m of gross floor area · S$351 per sq ft
- Parcel
- Punggol E12 Punggol Field Walk / Punggol East
- Site area
- 14,307 sq m
- Lease
- 99 yrs
- Plot ratio
- 3
- Gross floor area
- 42,921 sq m
- Sold as
- EC
Every bid — all 7, as HDB published them
| # | Tenderer | Bid | Behind the winner |
|---|---|---|---|
| 1 | Sing Holdings Limited | S$162,100,000 | — |
| 2 | JBE Holdings Pte Ltd | S$148,920,000 | S$13,180,000 · 8.1% |
| 3 | FCL Place Pte. Ltd. | S$143,880,000 | S$18,220,000 · 11.2% |
| 4 | Qingjian Realty (South Pacific) Group Pte Ltd | S$143,700,000 | S$18,400,000 · 11.4% |
| 5 | 5A Bellevue Properties Pte. Ltd. | S$141,000,000 | S$21,100,000 · 13.0% |
| 6 | 5B Mezzo Development Pte Ltd | S$141,000,000 | S$21,100,000 · 13.0% |
| 7 | CEL Property Pte Ltd | S$138,800,000 | S$23,300,000 · 14.4% |
What the land cost and what a unit sells for are not two ends of one sum. Between them sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold units. None of those is published for a named project, so this site does not estimate a developer’s cost or margin and no figure here should be read as one.
Source: HDB — Sites Sold by HDB · tender awarded 10 Dec 2012 · transcribed from HDB’s published tables on 2026-08-31 · prices are nominal and are not adjusted for inflation. HDB names the development on this row as “Waterwoods”. This parcel, from tender to today · Every land sale
What has been filed there since
Those two are not the same square foot. Gross floor area includes what nobody buys — the corridors, the car park, the plant rooms — so the land rate is spread across more area than a unit is sold by. The ratio is arithmetic on two published figures and is not a return, a profit, or an appreciation.
Year by year, for a median-sized unit
| Year | Median psf | Against the year before |
|---|---|---|
| 2021 | $1,052 (7) | — |
| 2022 | $1,144 (9) | +8.7% |
| 2023 | $1,241 (11) | +8.5% |
| 2024 | $1,304 (5) | +5.1% |
| 2025 | $1,366 (6) | +4.8% |
| 2026 | $1,490 (8) | +9.1% |
The two ends of this page are not two ends of one sum. Between the tender and the first unit sold sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold stock. None of those is published for a named project, so nothing here estimates a developer’s cost or margin and no figure on this page should be read as one. Why that is refused.
The rest of it
- Every filed transaction at WaterwoodsThe full record — price history, floor premium, what a sale would net