Palm Gardens
The ground under it was tendered in 1996. Both ends of that are public; nobody puts them together.
The land under Palm Gardens
HDB put this parcel out to tender and names Palm Gardens as what was built on it. Everything below is from that tender: the dates, the winning price, and the 6 bids that came in.
- Tender launched26 Jan 1996
- Tender closed28 Mar 19966 bids received
- Awarded13 May 1996SSL Properties Pte Ltd
- Winning tenderS$211,694,003HDB publishes no gross floor area for this site, so a rate per square foot cannot be worked out from what is published
- Parcel
- Choa Chu Kang S2 Choa Chu Kang Way
- Site area
- 30,671 sq m
- Lease
- 99 yrs
- Plot ratio
- 2.8
- Gross floor area
- Not published
- Sold as
- Condominium
Every bid — all 6, as HDB published them
| # | Tenderer | Bid | Behind the winner |
|---|---|---|---|
| 1 | SSL Properties Pte Ltd | S$211,694,003 | — |
| 2 | City Developments Limited | S$208,000,000 | S$3,694,003 · 1.7% |
| 3 | Success Development Pte Ltd / Vasilon Pte Ltd | S$203,701,000 | S$7,993,003 · 3.8% |
| 4 | Richdeal Investment Pte Ltd | S$173,081,000 | S$38,613,003 · 18.2% |
| 5 | Allgreen Properties Ltd / Hoe Seng Company Pte Ltd | S$168,898,000 | S$42,796,003 · 20.2% |
| 6 | First Capital Corporation Ltd / Guobena Sdn Bhd | S$138,670,000 | S$73,024,003 · 34.5% |
What the land cost and what a unit sells for are not two ends of one sum. Between them sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold units. None of those is published for a named project, so this site does not estimate a developer’s cost or margin and no figure here should be read as one.
Source: HDB — Sites Sold by HDB · tender awarded 13 May 1996 · transcribed from HDB’s published tables on 2026-08-31 · prices are nominal and are not adjusted for inflation. HDB names the development on this row as “Palm Gardens”. This parcel, from tender to today · Every land sale
What has been filed there since
Year by year, for a median-sized unit
| Year | Median psf | Against the year before |
|---|---|---|
| 2021 | $805 (9) | — |
| 2022 | $847 (24) | +5.2% |
| 2023 | $1,045 (12) | +23.4% |
| 2024 | $1,059 (18) | +1.3% |
| 2025 | $1,051 (20) | -0.8% |
| 2026 | $1,062 (6) | +1.0% |
The two ends of this page are not two ends of one sum. Between the tender and the first unit sold sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold stock. None of those is published for a named project, so nothing here estimates a developer’s cost or margin and no figure on this page should be read as one. Why that is refused.
The rest of it
- Every filed transaction at Palm GardensThe full record — price history, floor premium, what a sale would net
- Every land sale since 1993441 URA sites and 216 from HDB, with every losing bid that was published
- Why there is no margin on this pageWhat sits between the two ends, and why none of it is published