Bishan Loft
The ground under it was tendered in 2000. Both ends of that are public; nobody puts them together.
The land under Bishan Loft
HDB put this parcel out to tender and names Bishan Loft as what was built on it. Everything below is from that tender: the dates, the winning price, and the 5 bids that came in.
- Tender launched28 Jun 2000
- Tender closed24 Aug 20005 bids received
- Awarded15 Sep 2000NTUC Choice Homes Co- operative Ltd & Chip Eng Leong Enterprise Pte Ltd
- Winning tenderS$114,888,889HDB publishes no gross floor area for this site, so a rate per square foot cannot be worked out from what is published
- Parcel
- Bishan E2 Bishan St.11
- Site area
- 17,985 sq m
- Lease
- 99 yrs
- Plot ratio
- 2.8
- Gross floor area
- Not published
- Sold as
- EC
Every bid — all 5, as HDB published them
| # | Tenderer | Bid | Behind the winner |
|---|---|---|---|
| 1 | NTUC Choice Homes Co-Operative Ltd & Chip Eng Leong Enterprise Pte Ltd | S$114,888,889 | — |
| 2 | Centrepoint Properties Ltd | S$110,000,000 | S$4,888,889 · 4.3% |
| 3 | City Developments Ltd | S$97,000,000 | S$17,888,889 · 15.6% |
| 4 | Wingrand Investment Pte Ltd | S$96,388,000 | S$18,500,889 · 16.1% |
| 5 | Ho Bee Developments Pte Ltd | S$94,800,000 | S$20,088,889 · 17.5% |
What the land cost and what a unit sells for are not two ends of one sum. Between them sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold units. None of those is published for a named project, so this site does not estimate a developer’s cost or margin and no figure here should be read as one.
Source: HDB — Sites Sold by HDB · tender awarded 15 Sep 2000 · transcribed from HDB’s published tables on 2026-08-31 · prices are nominal and are not adjusted for inflation. HDB names the development on this row as “Bishan Loft”. This parcel, from tender to today · Every land sale
What has been filed there since
Year by year, for a median-sized unit
| Year | Median psf | Against the year before |
|---|---|---|
| 2022 | $1,365 (5) | — |
| 2023 | $1,379 (2) | +1.0% |
| 2024 | $1,597 (3) | +15.8% |
| 2025 | $1,742 (4) | +9.1% |
| 2026 | $1,741 (2) | -0.1% |
The two ends of this page are not two ends of one sum. Between the tender and the first unit sold sit construction over a multi-year build, financing, the development charge, marketing and agent commissions, GST, and the cost of holding unsold stock. None of those is published for a named project, so nothing here estimates a developer’s cost or margin and no figure on this page should be read as one. Why that is refused.
The rest of it
- Every filed transaction at Bishan LoftThe full record — price history, floor premium, what a sale would net
- Every land sale since 1993441 URA sites and 216 from HDB, with every losing bid that was published
- Why there is no margin on this pageWhat sits between the two ends, and why none of it is published